City of North Ridgeville
Mayor's Message
Sign Up for eNewsletter
Sign Up for Emergency Alerts
Economic Development
Employment
Pay Ticket Online
Pay Utility Bill
Parks & Recreation

Center Ridge Road Reconstruction Project Update

The Center Ridge Road reconstruction project is nearing completion.  The following is the milling and paving schedule planned for the coming weeks (weather permitting). Please note: Traffic will be maintained during all operations; however, you may experience delays. 

Milling Schedule
May 24 - May 27, 2021:  Milling will take place on Center Ridge Road during the hours of 7 AM to 5 PM
May 28, 2021:  Milling at SR 83 and various side streets during the hours of 7 PM to 5 AM
June 1 - 2, 2021:  Milling various side streets during the hours of 7 AM to 5 PM

Paving Schedule
June 1 - 3, 2021:  Paving mainline (Center Ridge Road) during the hours of 7 PM to 5 AM
June 4, 2021:  Paving SR 83 and various side streets during the hours of 7 PM to 5 AM
June 7 - June 9, 2021:  Paving various side streets during the hours of 7 AM to 5 PM

After completion of the surface course, permanent traffic striping will be added and all traffic signals will be programmed and activated.  This schedule is subject to change depending on weather conditions.

Print This Article
© 2024. City of North Ridgeville – 7307 Avon Belden Road, North Ridgeville, OH 44039 – (440) 490-2042