Catch Basin Repairs Project To Begin September 30, 2024

Denes Concete, Inc. will begin catch basin repairs starting the week of September 30 with an anticipated completion date of mid-to-late October. The project includes concrete replacement and structural repair of 48 catch basins at various locations. See the tentative schedule and location maps below.

September 30-October 4 - Location Map A
October 7-October 11 - Location Map B
October 14-October 18 - Location Map C

Two-way traffic will be maintained at each location; cones will be used when necessary.