Street Repairs and Paving Schedule 2018
Street Repairs
The City will see over $1.5 million in street repairs this year with the City’s share coming in at approximately $1.2 million.  The City does recognize that not all streets can be done but has prioritized the list of streets that will be paved this year within the budget limitations.
 
As part of the Ohio Department of Transportation (ODOT) Urban Paving Program, portions of Lorain Road/Route 10 will be paved.  Lorain Road will be repaved from the Ohio Turnpike ramps to the Cuyahoga County line, including the I-480 ramps. The intersection of Lorain/Lear Nagle/Cook will be excluded as it was done last year as part of the Lear Nagle Road widening project. In addition, Lorain Road west of Route 83 to Alternate 83, and across Alternate 83 to Chestnut Ridge Road will be repaved.  ODOT will be paying for 80% of the paving items, leaving the City’s share at approximately $307,463. This project is scheduled to begin in July or early August. 
 
Depending on weather conditions, the Service Department will begin paving as early as May the following streets at a total cost of approximately $600,000.  When the schedule becomes available, you’ll find the latest updates here.
 
To Be Completed/In Progress: 
Leslie Avenue - Prepping/Milling to begin October 11 followed by paving tentatively the week of November 5 (dates are subject to change depending on weather conditions)
Westwood Drive - Prepping/Milling to begin October 25 with paving tentatively scheduled for October 31 (dates are subject to change depending on weather conditions)
 
Completed:
Bender Road - Prepping/Paving to begin the week of July 9 with an expected completion date of August 3 (subject to change depending on weather conditions)
Branch Street - Prepping/Milling week of May 28; Base Coat pouring and paving/top coat the week of June 4; Driveways/Road edging will be addressed the week of June 4 (subject to change depending on weather conditions)
Cornell Avenue (southern half) - Prepping/Milling May 2, 3; Base Coat pouring May 16 and paving/top coat the week of May 21; Driveways/Road edging will be addressed the week of June 4 (subject to change depending on weather conditions)
Fern Tree LanePrepping/Milling scheduled for August 7, 8 with paving to begin the week of September 4 (dates are subject to change depending on weather conditions)
Gate Moss Oval - Prepping/Milling scheduled for August 7, 8 with paving to begin the week of September 4 (dates are subject to change depending on weather conditions)
Leafy Mill Lane - Prepping/Milling scheduled for August 7, 8 with paving to begin the week of September 4 (dates are subject to change depending on weather conditions)
Mills Industrial Parkway - Milling June 14; Prepping June 15 and the week of June 18; Paving week of June 25 (subject to change depending on weather conditions)
Olive Avenue (southern half) - Prepping/Milling May 2, 3; Base Coat pouring May 18, 21 and paving/top coat the week of May 21; Driveways/Road edging will be addressed the week of June 4 (subject to change depending on weather conditions)
Wallace Blvd. (southern half) - Prepping/Milling May 2, 3; Base Coat pouring May 17, 21 and paving/top coat the week of May 21; Driveways/Road edging will be addressed the week of June 4 (subject to change depending on weather conditions)
West Point Drive - Prepping/Milling to begin the week of September 4 with paving to following; paving is tentatively scheduled for the week of October 15 (dates are subject to change depending on weather conditions)
 
In addition, the City will spend nearly $300,000 this year on full-depth concrete repairs primarily on Highland Drive and Denise Drive.